Roofing complete + Air Con in

We did a trip to the house today to see how much had been done this week and were pleasantly surprised that 1. We had tradies on site working  and 2. the air con had been installed sometime late in the week!

Speaking to our SS earlier in the week he said we were looking at about 3 months. That will put us in around late August which will be a month over our contract date. I’m not surprised considering we lost 10 weeks in the beginning waiting for the slab to be poured.

The electrician is due back on site on Tuesday to finish roughing in and I”m hoping the cladding goes up early next week before the rain hits. Once that is on the exterior is then pretty much complete.

Here’s a bit of a photo update now the exterior is almost complete.

Advertisements

Bricks + Upper Roof Complete

Some good progress since my last post with the bricks completed on 14 April and the upper roof complete on 27 April. Fascias, guttering, eaves, some downpipes and whirlybirds are also installed.

I was hoping by now the cladding would also be on so the external paint could be done and upper bricks cleaned once the scaffolding comes down. Our SS has been on holidays and is back tomorrow so hopefully then I will have a better idea of when to expect the next wave of work.