Living in the house

It’s been a while since I posted. To be honest the last few weeks of the build just left me feeling completely deflated and over the entire thing so I wasn’t in the mood to post any updates.

We’ve been in the house for a few weeks now. We love the space and are really happy with the layout we designed and all our selections. It’s still really disappointing though when you look around the house and see the poor quality of work on a lot of things. It’s just not how a brand new house should be finished by a team of so called “professionals”.. I use that term loosely.

Here’s a few examples of the “quality” workmanship we paid for.

We are still waiting for our shutters to be installed which should be in the next few weeks, so once that it done I will take some better photos to post.

Our driveway is under construction at the moment and will be poured on Friday/Monday which will make a huge difference to the front of the house. No more having to get out of the car in the dirt! Our retaining walls at the back are now also complete so next up there is the back fence then we can get started on a bamboo screen on the top tier and some turf.

 

img_3881 img_3880 img_3870

 

Advertisements

Bathrooms + Electrical Underway

Last week saw the bath and toilets all installed. The bath installation meant getting yet another hole cut in our laundry ceiling because the plumbers had never actually plumbed the bath in even though we had told our supervisor numerous times. The supervisor asked them to go check a few weeks back and they said it was fine. It appears we were right!

Electrical kicked off on Thursday afternoon. All the downlights and powerpoints/light switches are in. Unfortunately they couldn’t do anything in the bathrooms yet as the ceilings are going to have another layer of gyprock so the cornices sit lower and cover the tops of the tiles (which aren’t straight). They still have quite a bit of stuff to do outside too. One of my kitchen pendants is also not hanging straight. Hopefully I can get that sorted out.

The gyprocker should be back (for about the sixth visit) sometimes this week. He has a fair bit of stuff on his list to get sorted. Tiler was there yesterday ripping down the kitchen splashback tiles (some of which were laid upside down and therefore didn’t line up!). The gyrocker will also have to redo that whole area before it can be retiled.

One coat of paint has been done but we still need another coat plus the girls feature walls to be done. There is paint on literally every surface. All over the tiles (as you can see in the photo of the bath), on the kitchen cupboards, all over the glass on my glass doors plus on the bricks. I think my five year old could have done a tidier job.

Not sure when the bricks are going to be redone around the front door. The list of stuff to be fixed just keeps growing and growing. Who knows when we will finally get the keys.

IMG_3359

IMG_3356

IMG_3347

IMG_3319

 

Internals on their way

After no progress last week, it was good to see some tradies back on site this week.

Cornices and sanding was done yesterday plus the start of our staircase went in today. Tomorrow should hopefully see the kitchen start going in which I am a tad excited about!

Not the most exciting photos at this stage but here are a couple anyway.

img_9310

img_9242

img_9311

img_9244

img_9237

img_9235

img_9234

Roofing complete + Air Con in

We did a trip to the house today to see how much had been done this week and were pleasantly surprised that 1. We had tradies on site working  and 2. the air con had been installed sometime late in the week!

Speaking to our SS earlier in the week he said we were looking at about 3 months. That will put us in around late August which will be a month over our contract date. I’m not surprised considering we lost 10 weeks in the beginning waiting for the slab to be poured.

The electrician is due back on site on Tuesday to finish roughing in and I”m hoping the cladding goes up early next week before the rain hits. Once that is on the exterior is then pretty much complete.

Here’s a bit of a photo update now the exterior is almost complete.

Bricks + Upper Roof Complete

Some good progress since my last post with the bricks completed on 14 April and the upper roof complete on 27 April. Fascias, guttering, eaves, some downpipes and whirlybirds are also installed.

I was hoping by now the cladding would also be on so the external paint could be done and upper bricks cleaned once the scaffolding comes down. Our SS has been on holidays and is back tomorrow so hopefully then I will have a better idea of when to expect the next wave of work.

Bricks – half way there

We are now about half way with our bricks. The lower floor is pretty much complete except for the sections where there is a drop edge beam. They couldn’t go any higher there without scaffolding, which was delivered yesterday. Hopefully they don’t muck around getting the scaffolding up and they can get cracking with the second floor bricks.

Once the bricks started we found a few issues with the slab. The draftsperson had actually left a bit of slab off the slab plan (always handy!) so they have had to add more concrete to the pillar at the right hand side of the garage. The concreters measurements must have also been out as the right hand corner at the front we have 30mm overhang on one pillar, and then 30mm underhang on the other! Our SS wasn’t concerned and said it would all be fixed where needed.

The brickies seem to have done a pretty good job so far and we are happy with our brick selection, especially considering it was just in the standard range of bricks.

Now for some photos..

IMG_2292

IMG_2312

IMG_2317

IMG_2379

IMG_2378

IMG_2361

IMG_2362

IMG_2364

IMG_2363 IMG_2397 IMG_2395 IMG_2398

Frames!

Finally we are moving in the right direction. Monday the plumbers turned up to do all the external plumbing. We also got them to put in some additional drainage around the side and back of the slab to help deal with any runoff from being on a slope.

Wednesday the lower floor frames arrived as promised, with carpenters due on site the next day. I went past on Thursday expecting to see some action but it was a ghost town. Lucky they turned up on Friday and got the lower floor sorted.

It was good to be able to actually walk through the rooms and get a better idea of the size instead of just imagining!

IMG_2181

IMG_2183

IMG_2182